Weep Screeds and Stucco-to-Paver Interfaces on Pinellas Homes
A paver field that climbs over the stucco weep screed looks finished in photos and fails quietly in the wall. Pinellas houses take wind-driven rain. The weep is the drain for the drainage plane behind the stucco. Bury it in bedding sand and the moisture has nowhere to go except into the sheathing.
The rule we hold on every house slab
Finished paver elevation stays below the weep screed. If the existing slab is already too high, we do not “make it work” by banking sand against the wall. We drop the field, add an isolation joint, or introduce a step so the weep stays open. That conversation happens on the first site walk, not after the pallets land.
Isolation joint at the house slab so the deck and the wall can move separately.
A soldier course or border that can be lifted later without cutting stucco.
Downspout tie-ins that do not dump onto the weep line.
Sealant only where the detail calls for it, never as a smear over a buried weep.
Pool cages and screen rooms
Kick plates and cage posts often sit right on the detail that should remain open. We pitch the deck to a drain, leave weeps at the cage base, and keep the first paver course from acting like a dam against the house beam.
Have us check an existing buried weep
If your deck already covers the screed and the baseboard smells musty after storms, call 727-490-9798. We can lower a border course or rebuild the first four feet without tearing the whole field.
Comments